Deploy freezes & maintenance

Deploy freezes

A deploy freeze blocks deploys for a while, such as over a holiday, a launch or an incident.

Go to Team settings → Deploy freezes → Schedule a freeze and choose:

  • Starts and Ends, in your own time zone
  • Applies to: every project, every project with one Environment label (such as every Production project), or one project
  • Reason: optional, shown to anyone whose deploy is refused

While a freeze is in effect:

  • pushes don't deploy, and deploy hooks answer 409 with the reason
  • the Deploy and Redeploy buttons are turned off
  • rollbacks still work, so you can always go back to an earlier deployment
  • pull request previews still deploy

The page lists the freezes in effect now, the ones coming up, and the ones that ended in the last 30 days. Choose End now to lift a freeze early, or delete one that hasn't started.

Admins and owners manage freezes.

Deploy lock

To stop deploys of one project right away, with no end time, go to its Settings → General → Deploy lock and choose Lock deploys, with an optional reason. It works like a freeze, with the same exceptions for rollbacks and previews, and lasts until an admin chooses Unlock deploys. Use a freeze for planned pauses, and the lock for "stop everything until we've looked".

Maintenance mode

Maintenance mode shows visitors a "back soon" page, with HTTP status 503, while you migrate data or fix something. The app keeps running behind it.

Turn it on in the project's Settings → General → Maintenance mode, with an optional message for visitors. While it's on:

  • your team can still reach the site with the Team link, which works for 12 hours in each browser
  • deploys still work, so you can ship the fix and check it through the team link
  • uptime checks are paused, so you aren't alerted for a page you chose to show

Turn it off from the same place. Developers, admins and owners can turn maintenance mode on and off.